Construction Updates
Updated February 9, 2010
Neuilly Plaisance Plaza Project: Installation of all of the wrought-iron fencing at Neuilly Plaisance Plaza was completed this week. The snowy and cold weather in early February prevented the installation of several movable wrought iron gate enclosures originally scheduled for the week of February 8. The installation of these wrought iron enclosures is now tentatively set for installation during the week of February 15.
Montgomery Park Pathway: Work completed thus far on the Montgomery Park walkway project includes all excavation as well as placement of the stone base for the pervious brick pavers. As of February 5 approximately 65% of the pervious brick paver walkway has been installed. The snowy and cold weather that began on February 5 has required work on the project to be be put on hold and that the area under construction be fenced off until construction of the brick paver walkway can resume once weather and conditions permit.